Course Update for December 6, 2013

15th Hole December 6 2013 15th Hole December 6 2013 15th Hole December 6 2013
It has been a busy week of construction on the new 15th hole. All the trees have been cleared and chipped, and stumps have been removed and will be taken offsite next week. The creek work has progressed nicely; with another week of weather like this, the re-configuring of the creek will be completed. All the rock for the new creek banks and plantings will be installed and straw mulch applied for winter erosion control. The Helical Piles for the new bridge have been installed and concrete footings will be poured Friday, the final bridge abutments will be poured next Tuesday, and the bridge will be put in place sometime in January. Overall, great progress has been made on the project to date.

Ian McQueen, Course Superintendent